Nextsource Materials Inc. announces that it has filed amended and restated unaudited condensed interim financial statements and management's discussion and analysis for the nine and three months ended March 31, 2023, and 2022 , which amends and restates the previously filed unaudited condensed interim financial statements and MD&A for the nine and [...]
Nextsource Materials Inc. is pleased to announce that commissioning of the Company's Molo Graphite Mine in Madagascar has been initiated and the installation of the solar and battery facility for the hybrid power plant is in progress. The hybrid power plant consists of a thermal generation facility, which is already in operation, and a solar and [...]
Nextsource Materials Inc. is pleased to announce its global anode expansion strategy and the economic results from the study relating to its first battery anode facility to be located in Mauritius. The highlights are as follows: Plans to construct, in stages, multiple BAFs globally in key jurisdictions that would be capable of producing commercial [...]
Nextsource Materials Inc. is pleased to announce that construction of the processing plant and mining camp for the Company's Molo Graphite Mine in Madagascar is now complete, and that the entire mining fleet is at site. President and CEO, Craig Scherba, commented: "We are now entering the final stages of development of Phase 1 and are fast [...]
Nextsource Materials Inc. is pleased to announce the results of the Annual and Special Meeting of Shareholders held virtually at 10:00 AM Toronto, Ontario, Canada on December 5, 2022. The Board of Directors had fixed October 14, 2022 as the record date for the Meeting. There were 101,872,614 common shares outstanding and entitled to vote at the [...]
Nextsource Materials Inc. is pleased to provide an update on the development of its Molo Graphite Mine in Madagascar, management appointments and progress on its proposed Battery Anode Facility deployment plans. The Company also announces the early exercise by Vision Blue Resources Limited of 23,214,286 warrants acquired in May 2021 for aggregate [...]
Nextsource Materials Inc. is pleased to provide a progress update for Phase 1 of the Molo Graphite Mine in Madagascar. The Processing Plant has arrived and been unloaded at the local port of Fort Dauphin in Madagascar and has cleared customs. Company-appointed logistics specialists have now commenced transporting all modules of the Processing [...]
Nextsource Materials Inc. is pleased to provide a site works update and to announce that a Madagascar subsidiary of CrossBoundary Energy has commenced the construction process for the solar and battery hybrid power plant for Phase 1 of the Molo Graphite Mine in Madagascar after the Company executed a definitive energy services agreement with [...]
Nextsource Materials Inc. is pleased to announce that its construction team is now setup at the Molo Graphite Mine site in Madagascar and civil and earthworks have been initiated in preparation for the delivery and installation of the processing plant. The offsite fabrication and construction of the auxiliary buildings and structures has also been [...]
Nextsource Materials Inc. is pleased to announce the results of a Preliminary Economic Assessment for an enhanced Phase 2 expansion of its 100%-owned Molo Graphite Mine Project in southern Madagascar. The PEA considered an enhanced Phase 2 expansion consisting of a stand-alone processing plant with a production capacity of 150,000 tonnes per annum [...]
Nextsource Materials Inc. is pleased to announce that Factory Acceptance Testing and final verification of equipment design specifications and end-to-end functions of the processing plant for Phase 1 of the Molo Graphite Mine is complete. The Processing Plant was designed and built using an all-modular approach and is capable of processing 240,000 [...]
Nextsource Materials Inc. is pleased to announce that fabrication and assembly of the processing plant for Phase 1 of the Molo Graphite Mine has been completed by our Engineering, Procurement and Construction contractor in their off-shore assembly facility and that Factory Acceptance Testing has been initiated. The Processing Plant has been [...]